Date |
Category |
Event |
1/7/2018 |
Work |
Started building livestock gate to lower pasture ( link ) |
1/8/2018 |
Work |
Cleared the driveway to the upper pasture ( link ) and finished gate |
2/8/2018 |
Corporate |
Created our property holding LLC |
2/21/2018 |
Land purchase |
Closed on additional 6 acres parcel ( 02917-013-011 ) |
3/28/2018 |
Work |
Continued clearing the tree line between service road and lower pasture |
4/13/2018 |
Work |
Installed posts on property corners ( link ) |
|
Architect |
Initial meeting with architect on workshop / garage |
4/28/2018 |
Work |
Cleared alternate driveway to the lower pasture for land clearing ( link ) |
4/30/2018 |
Work |
Set flags for the alternate driveway through our lower pasture |
5/1-3/2018 |
Work |
Contracted land clearing service removed tree line between service road and upper pasture ( see before/after shots from land clearing ) |
5/9/2018 |
Work |
Removed flags for alternate driveway and continued clearing tree line between service road and lower pasture (w/ ma) |
5/10-11/2018 |
Work |
Continued clearing tree line between service road and lower pasture (w/ ma) |
5/11/2018 |
Architect |
Received first draft from the architect for our workshop/garage |
5/17/2018 |
Work |
Continued clearing tree line between service road and lower pasture |
|
Architect |
Second meeting with architect on workshop / garage |
5/24/2018 |
Architect |
Second draft from the architect after feedback and second meeting for workshop/garage. |
5/31/2018 |
Work |
Continued clearing tree line between service road and lower pasture ( link ) |
6/4/2018 |
Corporate |
Created our farm business LLC |
6/6/2018 |
Work |
Continued clearing tree line between service road and lower pasture |
6/8/2018 |
Architect |
Third draft from the architect for the workshop/garage |
6/9-10/2018 |
Work |
Continued clearing the tree line between service road and the lower pasture (w/ Derek) ( link ) |
6/16-17/2018 |
Work |
Land clearing work |
6/26/2018 |
Architect |
Fourth draft with the architect, now with some electrical portions includefd, for workshop/gara |
7/26/2018 |
Building Planning |
Submitted toolshed building permit documents |
7/26-28/2018 |
Training |
Organic Conference in Gainesville, run by Florida Organic Growers |
8/2/2018 |
Buliding Planning |
Met with building permit office regarding toolshed |
|
Work |
Continued clearing, below the service road at the top of the lower pasture |
8/6/2018 |
Building Planning |
Received approved toolshed building permit, and address for the main parcel |
8/7/2018 |
Planning |
Met with ag office to discuss grants and cost shares. |
8/17/2018 |
Equipment |
Completed purchase of our Mahindra 5570 4WD tractor |
|
Work |
Used tractor to clear parts of the upper pasture and mow |
8/25-26/2018 |
Work |
Continued clearing around service road and mowing upper pasture |
9/1-2/2018 |
Work |
Work clearing tree line and beginning to clear the area for the toolshed |
9/6-7/2018 |
Training |
Attended Small Ruminant Workshop in Gainesville (IFAS / County Ag) |
10/6/2018 |
Work |
Land clearing work |
11/3/2018 |
Training |
Attended Beginning Beekeeping Workshop in Gainesvile (IFAS / County Ag) |
11/9-10/2018 |
Work |
Work clearing tree line and mowing upper pasture |
11/15/2018 |
Architect |
Met with architect again to look at the workshop/garage plan. |
11/17/2018 |
Work |
Finalized the change for the upper pasture planning, so toolshed will not be built where planned |
12/2/2018 |
Work |
|
12/5/2018 |
Architect |
Received preliminary final draft from architect for the workshop/garage plan, prior to engineering |
12/17/2018 |
Work |
ALMOST done with clearing around the service road |